#5Multiple Choice

Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday.
Why may this be the case?

Previous
Question 5 of 70
Exam AD0-E903 Topic 1 Question 5