Home/Exams/Microsoft Managing Projects with Microsoft Project 2013/Question #4
#4Multiple Choice

Your company uses Project Professional 2013.
You are setting up a preliminary schedule by using manually scheduled tasks. You create a task with no duration, start, or finish date, and then you assign a resource. Later, you enter a duration of three days for that task.
You need to let the resource know how the Work will be affected.
What should you say?