#9Multiple Choice

You are a project manager for a software development company. You use Project Professional 2013.
You manage an integration project, and you discover that you need to add additional resources to the integration tasks in order to meet your development complete milestone date. The project is behind schedule, so you must shorten the duration of the integration development work.
You identify two additional resources to work on the integration task. When you add these resources, your task now shows it will complete three days ahead of schedule, which leaves a contingency window for issues that may arise.
In order to shorten the duration of the task when the resources are added, you need to set the task type before adding the resources.
What should you do?

Previous
Question 9 of 101
Exam 74-343 Topic 1 Question 9
Back to all questions
Next
GrabCert

Your trusted source for certification exam preparation. Pass your exams with confidence.

Quick Links

  • Home
  • Exams
  • Providers

Legal

  • About
  • Contact Us
  • Refund Policy
  • Privacy Policy
  • Terms of Service

© 2026 GrabCert. All rights reserved.

Sign InSign Up