An administrator needs to create and start five new VMs for a Data Analytics Project (OLAP). The VM Profile is as follows:
✑ vCPU:4
✑ vRAM: 64 GB
✑ vDisk: 1.5 TB
Each of the four nodes of the Nutanix cluster has the following:
✑ 24 vCPU. 20% overall usage
✑ 192 GB RAM, 60% overall usage
✑ 2 x l920 GB SSD
✑ 4 x 2 TB HDD
At cluster level, there is a single RF2 container that is 30% utilized and has an extent store capacity of 13.5 TB.
Which component requires administrator attention?

Previous
Question 7 of 99
Exam NCM-MCI Topic 1 Question 7
Back to all questions
Next
GrabCert

Your trusted source for certification exam preparation. Pass your exams with confidence.

Quick Links

  • Home
  • Exams
  • Providers

Legal

  • About
  • Contact Us
  • Refund Policy
  • Privacy Policy
  • Terms of Service

© 2026 GrabCert. All rights reserved.

Sign InSign Up