#9Multiple Choice

During Sprint Planning the Product Owner and the Developers are unable to reach an understanding about the highest order Product Backlog items. Because of this, the Developers are unable to determine how many Product Backlog items they can forecast for the upcoming Sprint. However, the Product Owner and the
Developers are able to agree on a Sprint Goal.
Which of the following actions should the Scrum Master support? (Choose two.)