When can a user choose from multiple rate types for their work, while logging a time card?
A.
Only if this capability is enabled in the Project Record
B.
Only one (1) rate type can apply
C.
Only if the capability is enabled in the Time Sheet Policies
D.
Only if the capability is enabled in the Project Preferences