Home/Exams/CMAA Certified Construction Manager/Question #5
#5Multiple Choice

An owner has purchased land and is currently in the planning phase for a new $50 million office building project using design-build delivery. The location of this project is in a flood zone. The cost to improve resiliency protection exceeds the project budget by $6 million.
Which of the following options is the FIRST recommendation the agency CM should give the owner?

Previous
Question 5 of 173
Exam CMM Topic 1 Question 5
Back to all questions