A contractor is rehabilitating a bridge over a navigable waterway. The construction contract allows for the navigable channel to be closed for pier repairs for short durations, provided that the channel can be cleared within one hour of a Coast Guard request. Failure to do so will result in a hefty fine and project shutdown. The contractor decides to hire a tug boat with operator on standby for the length of the project to better facilitate swift removal of work barges from the channel.
This scenario BEST describes use of which risk response?

Previous
Question 6 of 173
Exam CMM Topic 1 Question 6
Back to all questions
Next
GrabCert

Your trusted source for certification exam preparation. Pass your exams with confidence.

Quick Links

  • Home
  • Exams
  • Providers

Legal

  • About
  • Contact Us
  • Refund Policy
  • Privacy Policy
  • Terms of Service

© 2026 GrabCert. All rights reserved.

Sign InSign Up