You are the product owner for a new application. You have the list of product backlog items (PBIs) with assigned business values for the first release of the application. You will be working with an established scrum master and development team. You know the teams capacity and the planned sprint duration.
You need to plan the release schedule based on your existing backlog.
Which three actions should you and the team perform? (Each correct answer presents part of the solution. Choose three.)