You manage a development team that uses the Microsoft Visual Studio Scrum 2.0 process template.
You establish a product backlog, allocate backlog items for a sprint, and define the tasks required to complete the sprint.
You need to ensure that the agreed upon work is assigned to team members.
Who should be responsible for assigning work to team members?