Question #4
#4
Multiple Choice
Mark for review
How should product-based planning be used as part of PRINCE2 Agile?
A.
To track progress against the team plan
B.
To create the project plan using empiricism
C.
To enable team planning to be predictive
D.
To plan by focusing on the features required