Which statement about the 'directing a project' process is CORRECT?
A.
The project board should attend regular project progress meetings
B.
The project board should make decisions based on the Agilometer risks
C.
A project board member should fulfill the product owner role within a delivery team
D.
The project board should increase the stage-level time tolerance