Which is the purpose of the Change theme?
A.
Prevent change to baselined products
B.
Identify, assess and control any potential and approved changes to baselined products
C.
Establish mechanisms to monitor and compare actual achievements against those planned
D.
Assess and control uncertainty
Reveal Answer