Why is a Project Brief produced?
A.
To act as a trigger for the Starting up a Project process
B.
To record the strategies and management controls to be used by a project
C.
To provide a full and firm foundation for the initiation of a project
D.
To be used by the Project Board as a basis for reviewing the progress of a project